top of page
  • Writer's pictureBrian Boelk

Sidewalks Nearing Completion

All safety rail and stair handrail have been installed. The contractor continues to pour the remaining sidewalks west of Greene Street, that were unable to get completed prior to winter hitting last Fall. Following the completion of the sidewalks, the contractor will get rolling on final grading and restoration (seeding) so that we can get this project wrapped up, site cleaned, and open and available to all.




4 views0 comments

Recent Posts

See All

And the Heat keeps coming

Just wanted to update everyone that we are going to push back the tilling, final grading, and seeding to the 2nd or 3rd week in September due to the projected weather, which is hot and dry. Weed and f

Restoration is on the way!

Despite the extreme heat we are experiencing this week, you will soon be seeing some action taken on remaining restoration and clean-up along Third Street. Due to weather and specifications, the cont

bottom of page