Railroad Park will be closed to the public Wednesday through Saturday of this week, May 17-20, for repairs to the PIP play surface. Sorry for the inconvenience and thank you for your understanding and cooperation.
Just a reminder to everyone that final grading, seeding, and restoration will be taking place over the next 2-3 weeks pending weather. If you are east of Greene Street, the contractor will go through
Quick update on the 3rd Street construction: All sidewalks have been finished. PCI has been completing additional grading the past couple of days, and plan to continue to work on topsoil for the next